Canal crossing Preston 1

Canal crossing at Preston (PWDR)

Project Overview
HIGHWAYS
Client Lancashire County Council
Contractor Costain
Start Date 01/01/2019
Project Value £7.4M
Description A project to install a twinwall pipe across the Lancaster Canal, as part of the build of the Preston Western Distributor Road, including careful consideration of environmental impacts.

Lancashire County Council are building a major new road - the Preston Western Distributor, which will link Preston and southern Fylde to the M55 motorway.

Led by main contractor Costain, the £200m scheme will increase capacity on the existing local road network via the construction of a new motorway junction, four new bridges and three underpasses.

As the pipework and drainage contractor, SGC Civil Engineering were responsible for the installation of a 450mm twinwall pipe across the Lancaster Canal. This involved close collaboration with both Costain and the Canal & River Trust to schedule works to minimise disruption to narrowboats using the water, as well as protect the wildlife in the area.

The installation consisted of damming off the canal using a portadam and then setting up a large overpumping system consisting of 3 x 12’’ pumps, complete with appropriate telemetry. This was crucial as the Lancaster Canal has no lock gates, so failure would have had a devastating effect on the surrounding area.

Once the portadam had been installed and the overpumping was in operation, we could start to drain down within the portadam. At this stage we brought in a specialist fish rescue contractor to ensure we complied with the requirements of the Freshwater Fish Directive. Pike and Rudd were saved in the process.

Upon final drain down, we could install secondary measure stanks to ensure the safety of the operatives and the preservation of the canal. After installation of the pipe across the canal, we reinstated the canal bed using specialist puddle clay to seal the area and renewed the clatter boards. The canal was then refilled and the area was made good.

The whole operation from start to finish took two weeks.

Setting up of portadam
Setting up of portadam
Excavation of silt within portadam
Installation of secondary stanks and excavation of canal
Installation of secondary stanks and excavation of canal
Installation of trench box to install 450mm twinwall pipe
Installation of 450mm twinwall pipe under the canal
Installation of clatter boards and puddle clay once the pipe had been installed
Removal of portadam

Setting up of portadam

Setting up of portadam

Excavation of silt within portadam

Installation of secondary stanks and excavation of canal

Installation of secondary stanks and excavation of canal

Installation of trench box to install 450mm twinwall pipe

Installation of 450mm twinwall pipe under the canal

Installation of clatter boards and puddle clay once the pipe had been installed

Removal of portadam

Talk to us

To ask us a question about your next project, please email enquiries@sgc.ltd. We will put you in touch with the best person to answer your query.